DataOne data center in Vineland, New Jersey (via Sustain SJ)

New Jersey hits data center powering Microsoft Copilot with $1m fine after drone expose 62 secretly-installed gas generators | Daily Reports Online

Share


  • New Jersey issues $1.07m fine for failure to obtain permits to run gas generators
  • DataOne campus running Microsoft’s AI was using 62 of them illegally
  • DataOne “disagree[s]” but has 45 days to obtain the relevant permits

A Microsoft partner has been hit with a $1.07 million fine by the US state of New Jersey after allegedly installing no fewer than 62 natural gas generators on-site without obtaining the correct environmental permits.


The state found out about the generators after a local farmer photographing a neighboring golf course noticed equipment appearing on the campus, which led to an investigation and the deployment of a thermal drone, which at the time, observed 45 of the 62 generators in operation.