Electrical pylons and high voltage power lines are behind a barbed wire fence. critical infrastructure

PSC wipes out 10 months of progress on Oracle’s 1.3 GW Wisconsin data center — pushing partial 310 MW power to late 2027 and full load to 2029 | Daily Reports Online

Share


  • Oracle’s Wisconsin campus may have finished buildings long before electricity arrived
  • Regulators withdrew their completeness finding after ATC filed 564 additional documents
  • Ten months of review ended without a decision and restarted from zero

Oracle’s massive 1.3 GW AI data center campus in Wisconsin, dubbed Project Lighthouse, faces severe power delays after regulators restarted the review needed to connect it to the grid.


The campus in Port Washington is being developed by Vantage for Oracle, with four data centers planned across the site.